- Implementation of central public sector undertaking (CPSU) scheme phase – II for setting up 12,000 MW grid connected solar photovoltaic power projects by the government producers with viability gap funding support for self use or use by government / government entities either directly or through distribution companies (DISCOMs) from financial year 2019 – 20 to 2022 – 23.
Grid Connected Solar Power Projects: Key Points
The project cost for 12,000 MW solar
power project is estimated as Rs. 48,000 crore. The required VGF support for
this 12000 MW will be Rs 8,580 crore.
- The scheme will mandate use of both solar photovoltaic cells and modules manufactured domestically as per specification and testing fixed by MNRE.
- Any government producer setting up solar PV power project will be eligible for assistance under this scheme if solar PV plant for self use or use by government / government entities either directly or through DISCOMs.
- The viability gap funding shall be provided covering the difference between the domestically produced solar cells and modules and imported solar cells and modules.
Incentives - Grid Connected Solar Power Projects
- The permissible maximum VGF has been kept at Rs. 0.70 Cr / MW ( Rs. 0.55 Cr/MW from 10th May, 2021 ), the actual VGF to be given under the scheme would be decided through bid parameter. The VGF will be released in two trenches (1) 50% on award of contract to EPC contractor (2) Balance 50% on successful commissioning of full capacity of project.
- The solar energy corporation of India (SECI) will be charged a fee of 1% of the VGF disbursed for conducting bidding, handling funds, monitoring project and managing all aspects of the scheme.
- The power produced by this scheme can be used for self-use or use by government entities either directly or through DISCOMs on payment of charges not more than Rs 2.80 per unit ( Rs 2.45 per unit from 10th May, 2021 )
Grid Connected Solar Power Projects Time Line
- 500 MW Projects: Projects to be commissioned within 24 months ( Rs 2.45 per unit from 10th May, 2021 )
- from the date of letter of award for projects up to 500 MW
- More Than 500 MW Projects: Capacity of 500 MW to be commissioned within 24 months from the date of letter of award and balance capacity to be commissioned within next 6 months